Most small contractors know their revenue. Fewer know what each job really earned once the labor, materials, dump fees and the extra trip to the supply house are added up. That is what job costing tells you. It is not a big-company accounting project. It is a habit: write down what a job costs while it is happening, then compare it with what you priced.
This guide walks through a simple job costing method you can run with a notebook, a spreadsheet or software, whether you pour flatwork, hang drywall or run a one-truck handyman business.
Job costing is tracking the costs of each job separately, so you can see the profit on that job instead of only the profit for the year. For every job you want three numbers:
When those three numbers sit side by side, patterns show up fast. Maybe your patio jobs make good money and your small repair calls barely cover the drive. Maybe one crew runs long on labor every time. You can't fix what you can't see.
Keep the categories simple and use the same ones on every job, so jobs can be compared with each other.
Overhead is different. Your truck payment, phone, insurance, software and office costs are real, but they don't belong to one job. Track them separately and cover them through your markup. If you spread them across every job by hand, the job numbers get muddy.
Every receipt, timesheet and invoice should carry the same job name or number. "Garcia driveway, Chino" works. So does a job number. The point is that a receipt found in the truck three weeks later still lands on the right job.
Your estimate is the budget. If you price with line items (labor, materials, subs, equipment), you already have the categories to compare against. Our guide on how to write a construction estimate in California shows how to build an estimate with clear line items.
The IRS's guide for new business owners (Publication 583) recommends recording expenses when they occur, and generally on a daily basis. That same habit makes job costing easy. Once a day, or at least once a week:
The IRS also lists the kinds of supporting documents a business should keep, including paid bills, invoices, receipts, deposit slips and canceled checks. Keeping them by job doesn't replace keeping them for taxes; it makes both jobs easier.
Publication 583 also recommends opening a business checking account and keeping it separate from your personal account. For job costing, this matters because a business card or account gives you one clean list of job purchases. Mixing a materials run with groceries on the same card is how costs go missing.
Extra work is where job profit leaks. When the homeowner adds a step or a wider pad, write it up as a change order with a price before you do the work, and add the extra cost to that job. Our California estimate guide covers the written-contract and change-order basics for home improvement work.
When the job is done and the final invoice is paid, total it up:
| Line | Estimated | Actual |
|---|---|---|
| Labor | ||
| Materials | ||
| Subcontractors | ||
| Equipment | ||
| Job fees | ||
| Total job cost | ||
| Amount invoiced and paid | ||
| Gross profit (paid minus cost) |
Then write one sentence: why the actual differed from the estimate. "Base took an extra day" or "Second trip for rebar." Those sentences are what make your next estimate better.
A common pricing mistake is confusing markup with margin. Here is a simple illustration (example numbers, not industry figures):
If you need a 25% margin to cover overhead and profit, you have to price higher than a 25% markup. Job costing shows you what margin you are really getting after the real costs come in.
Once you have closed out a handful of jobs, review them together:
JobTelesis is contractor software that keeps the revenue side of every job together. Each client file holds the estimate and the invoice, so the number you invoice matches the job you priced. You build estimates with line items, quantities and prices, email them as PDFs from your company name, create the invoice when the work is accepted, and record the receipt when you are paid. You can also track leads, jobs and clients from one place.
That gives you the "estimated" and "paid" columns for every job in one place. Keep your cost receipts and hours by the same job name in your spreadsheet or bookkeeping, and closing out a job takes minutes instead of an afternoon.
JobTelesis Basic is $35 a month in US dollars after a 14-day trial. Basic is the only plan. Start your 14-day trial.
Tracking the actual labor, materials, subcontractor, equipment and fee costs of each job separately, then comparing them with the estimate and the amount paid, so you know the profit on every job.
If you want to know which jobs are worth taking, yes. It doesn't need special training. A job name on every receipt and a weekly log of hours is enough to start.
Usually not job by job. Track overhead (truck, insurance, phone, office) separately and cover it with your markup. Ask your bookkeeper how they want it handled.
Markup is added to cost. Margin is profit as a share of the price. A 25% markup on a $4,000 cost gives a $5,000 price and a 20% margin.
The IRS says to keep records that support your tax return until the period of limitations runs out, which is generally 3 years and longer in some situations. Ask your tax preparer what applies to you.